I thought it would be helpful to share this letter following my request that the planned major utilities (SSE Major cabling upgrade) works on Lower Street are brought forward. I have consulted with my fellow town councillors and the Haslemere Chamber of Trade and Commerce, and agreed that the works should start as soon as possible in the hope that the works are completed before businesses in town are able to fully reopen.
This is the text of the letter:
I believe you are aware of the SSE Major cabling upgrade works on Lower Street which will require a Road Closure. These works were originally planned to take place this Summer Holidays, however I’ve been informed that you’ve asked if these works could be brought forward whilst the shops are still closed.
I’ve spoken to SSE and they can bring these works forward and have provided me with a planned start date of the 01/06/2020 (provided that you’re happy with this). The duration of the works will be 6 weeks (with the end date being 18/07/2020), however this is the worst case scenario and SSE are confident that they can complete the works quicker than this.
If they do get the go ahead, the Advanced Warning Signs will be placed on Monday 18th May and Letter drops carried out also on this date which gives members of the public and local residents/businesses plenty of notice.
The diversion route will be Tanners Lane, West Street, High Street which has been used before and works well. The parking bays outside the shops on West Street will have to be suspended.
Please could you advise if you would be happy with this?
Kind Regards,
Network Coordinator – Waverley
Streetworks Team
Network and Asset Management Group
Surrey Highways