Notifying residents of roadworks happening in Haslemere this month.
Tag Archives: Lower Street
Emergency utility works on Lower Street, Haslemere
Dear Councillor,
For your information can I advise you of emergency works being carried out on Lower Street, Haslemere (Jct with Tanners Lane).
BT need to renew the cabling to restore customers’ service. This section of cable serves 1200 customers. The traffic management that is placed is Multi-Way Signals and the estimated end date is the 28/10/2020.
We have requested manual control between 06:30-09:30 & 16:00-18:30 to minimise disruption as much as possible.
Kind Regards,
Network Coordinator – Waverley
Streetworks Team
Emergency utility works on Lower Street, Haslemere
Sent: 24 September 2020 10:37
To: Nikki Barton <Nikki.Barton@surreycc.gov.uk>
Subject: Emergency utility works on Lower Street, Haslemere
Dear Councillor,
For your information can I advise you of emergency works being carried out on Lower Street, Haslemere (Outside 66).
Thames Water need to repair a burst water main. The traffic management that is placed is Two-Way Signals and the estimated end date is the 30/09/2020.
We have requested manual control between 06:30-09:30 & 16:00-18:30 to minimise disruption as much as possible.
Kind Regards,
Network Coordinator – Waverley
Streetworks Team
Surrey Highways
Telephone: 01483 518035
For more information about what we do, please visit Surrey Highways website You can follow us on twitter @Surreytravel |
Update – Lower Street, Haslemere – SSE Works Mains Cable Replacement
I had a site meeting this morning with SSE management to discuss their works on Lower Street.
Lower Street will be opening on Monday morning, with traffic light controls as there is still work to carry out on one side of the carriageway as they have major hurdles to overcome- including extremely old multiple service pipes.
Traffic lights are expected for 2-4 weeks.
High Pavement works will then follow.
It’s disappointing that SCC Highways were not able to take the opportunity to resurface this stretch of road during the closure.
Lower Street Roadworks To Be Brought Forward In Haslemere
I thought it would be helpful to share this letter following my request that the planned major utilities (SSE Major cabling upgrade) works on Lower Street are brought forward. I have consulted with my fellow town councillors and the Haslemere Chamber of Trade and Commerce, and agreed that the works should start as soon as possible in the hope that the works are completed before businesses in town are able to fully reopen.
This is the text of the letter:
I believe you are aware of the SSE Major cabling upgrade works on Lower Street which will require a Road Closure. These works were originally planned to take place this Summer Holidays, however I’ve been informed that you’ve asked if these works could be brought forward whilst the shops are still closed.
I’ve spoken to SSE and they can bring these works forward and have provided me with a planned start date of the 01/06/2020 (provided that you’re happy with this). The duration of the works will be 6 weeks (with the end date being 18/07/2020), however this is the worst case scenario and SSE are confident that they can complete the works quicker than this.
If they do get the go ahead, the Advanced Warning Signs will be placed on Monday 18th May and Letter drops carried out also on this date which gives members of the public and local residents/businesses plenty of notice.
The diversion route will be Tanners Lane, West Street, High Street which has been used before and works well. The parking bays outside the shops on West Street will have to be suspended.
Please could you advise if you would be happy with this?
Kind Regards,
Network Coordinator – Waverley
Streetworks Team
Network and Asset Management Group
Surrey Highways
Update on Scottish Power works with temporary lights at Tanners Lane/Lower Street junction in Haslemere
This morning, I spoke on site with the Scottish Power project coordinator and crew who are working in Haslemere and have set up the temporary lights by the Lower Street and Tanners Lane junction.
They tell me they have extended their road closure licence until the 24th April for the temporary traffic lights. 24th April is the worse case scenario end date for the lights.
I explained that the current signage states the work will finish on 5th March and that it would be helpful to set expectations by amending the details on the board. They have agreed to do this.
The project has taken longer than expected due to complications. These have included cables at one building that were 8m down and required deep excavation, some pipes that had pushed into drains and, the poor weather.
They tell me the lights will be recalibrated in the next few days as the company will move their works to the other side of Lower Street.
I have arranged a further meeting with the site manager for next week to discuss further.
Lower Street Drain, Haslemere
Several residents brought to Surrey County Council’s attention the overflowing drain in Lower Street.
I have been out with the jetter at the Lower Street crossing, investigating the drainage problem. The drain has been jet washed and a camera probe sent down, revealing a blockage in the pipe under Lower Street. The team think it is probably a water utility pipe.
Next steps… SCC highways to obtain a street works permit to excavate the road in order to repair the problem.
Lower Street – road closure (resurfacing)
Here is an email I have received re Lower Street road closure:
From: On Behalf Of Works Communication Team/EAI/SCC
To: Nikki Barton <Nikki.Barton@surreycc.gov.uk>
Subject: Lower Street, Haslemere – Resurfacing works (Road Closed)
Dear Cllr Barton
I am writing to advise you that we will be closing the road on the 27 September and the 4 October whilst we carry out our surfacing works.
To facilitate this we will need to close the road from 9:30 until 16:00 on each Friday to enable us to park our lorry near to the site.
There will be no access for vehicles during this time.
Outside of the above closures, we will continue to use three way lights until the end of the works.
You and your residents can also find up to date details of the works on www.surreycc.gov.uk/roadworks
If you have any questions please do not hesitate to contact us on 0300 200 1003 or email works.communication@surreycc.gov.uk.
Kind regards
Works Communication Officer
Works Communication Team
Local Highways
Update: Lower Street works, Haslemere
I am sharing an update regarding works on Lower Street, Haslemere. The works within Lower Street itself are complete and the team have now moved into the garage area.
Prior to the works starting the team carried out site investigations of both the pipe systems and ground conditions. The ground condition survey had shown mild asbestos levels that were not sufficient to cause concerns with regard to safety. However, when the team started digging in the garage forecourt today, they found much higher concentrations of asbestos. As a result of this works had to cease.
The team now need to get positive confirmation it is asbestos, then assess the risks posed, and then proceed with appropriate measures in place to safely continue their works – this process may take some time. In the interim period the team will be working in other areas to maintain progress of the overall job at hand.
Update on Lower Street roadworks
From: on behalf of Works Communication Team/EAI/SCC <works.communication@surreycc.gov.uk>
Sent: 14 August 2019 14:20:36
To: Nikki Barton <Nikki.Barton@surreycc.gov.uk>
Subject: RE: Road works Lower St Haslemere
Dear Nikki Barton
Thank you for getting in touch. Firstly I would like to provide some background on the purpose of this work and the complications this scheme has presented.
The works on Lower Street involve construction of new drainage and are primarily to remove a flood risk to a property where the highways drains pass beneath it, by rerouting our pipes. This involves digging a new pipe through private land in a restricted area, between two houses and a garage parking area, through a retaining wall, along a footpath and to a chamber.
There are a great deal of utility services underneath the road surface (please see below pictures and map) and ultimately it is these services which actually dictate what is possible. Due to the significant amount of underground services the team are using a vacuum excavator as this is a far safer way for our team to remove spoil than a conventional digger. Using this equipment mitigates any risk to their personal safety, which is of utmost importance to us.
We have gatemen present at each end of Lower Street, their role is to remain at either end of the road and ensure the public do not enter the live works site. The area the team are working in is outside of a property called Tisa Cottage. Whilst they may not be visible from either end of the road, I can assure you that the team are on site, working extremely hard on a daily basis and are making progress.
On Monday I was advised that the team had got to a point where they have found the unknown buried pipe and this has determined the level for the rest of the works. Our engineer believes they have found a route through the services to allow installation of the new pipework and the team on site are working towards this. There are difficulties with some of the existing pipes which the new pipes need to be connected to, as they are encased in brick. This may mean that the team have to dig further to achieve the connections or do something a little differently. The excavations are a bit larger than initially hoped for but unfortunately this is unavoidable. Please see attached a copy of the original plans for this scheme which should demonstrate what the team set out to achieve.
Looking at the original plans it is clear that this a particularly difficult site with many utility services, this makes progress slow and the design has to be adapted to suit what is unearthed. The team had previously investigated as thoroughly as possible having camera surveyed the drain runs and used ground probing radar to identify services and hence a probable route for the new pipes, however it is only when the ground is actually excavated that the realities of the situation are revealed.
The equipment being used, the width of the road and the size of excavation required mean that a road closure is necessary. Another reason, that may not be immediately obvious, is that live traffic cannot run too close to the hole due to the pressure that is transmitted to the sides of the excavation by vehicles. We really don’t want to close roads unless we have to and do not make the decision lightly. There are many variables we have to consider including the site operations, the size of the road and the safety of both the travelling public and our work force. For Lower Street this criteria meant a closure.
Please see attached site diaries from the 7 and 8 August which detail work progress with photographic evidence of work taking place. Please be advised these site diaries belong to one individual on site and their start time does not necessarily reflect the time that everyone was on site.
The lead engineer on this project is satisfied with the progress on site. Considering the difficulties the team have faced, they are working extremely hard and going the extra mile where necessary to support the residents living in the works area, whilst carrying out their work to a good standard. I hope this help to reassure you and your residents that work is taking place and progress being made.
In view of the above, I will be updating our road works map pop-out with a PDF document that explains the work and has pictures of our progress so far. I hope that this will highlight to the public the challenges the team have faced on this scheme and the extent of works being carried out. I’m hoping that explaining what we are trying to achieve will justify the length of time we need for this work and why it is essential that the road is closed whilst we carry out the work.
I would be very grateful if you could direct your residents to the information on roadworks.org and if there are further queries please could they be sent to us in the Works Communications Team.
Kind regards
Works Communication Officer
Works Communication Team
Surrey Highways
Tel: 01483 404618