Tag Archives: Surrey County Council

Update – Sturt Road Repair – Haslemere

Works started today to resolve the recurring flooding problem under Sturt Road railway bridge, and associated road surface deterioration due to constant subsurface water saturation.

Project started as programmed end of 2016, but discovered a number of water leaks in Thames water pipes under this section of road, so project halted until repairs carried out.  Project then had to be rescheduled on program list, resulting in delay.

NB -Repair Sturt

Work that started today =  hand digging out trench as electricity and gas mains pipes to be avoided. Aim to lay new 150 mm pipe under Sturt Road to connect existing gullies, so that runoff is removed from the road.

Pipe will be laid and concreted in tomorrow, 16/03/2017. Road resurfaced 17/03/2017.

Road will be closed with diversions in place until 18/03/2017- but still full access to Haslemere Sports Centre and Sturt Road businesses.

I have organised for a vegetation gang to come in while the  road is closed to cut back vegetation, and clear mud and debris from the verges.

Sturt Road, Haslemere – Drainage Investigation Work – begins 14 March for one week

Recently advised that the drainage investigation works were due to start on Sturt Road, Haslemere.  Unfortunately these works will be delayed by 1 day as the council  was unable to get the permit for the 13/03/17.  I can advise that these works will now begin on the 14/03/17.

Information leaflet here.

The council will keep the residents informed by updating its advanced warning signs.

Residents can also find up to date details of the works on www.surreycc.gov.uk/roadworks

If you have any questions please do not hesitate to contact us on 0300 200 1003 or email works.communication@surreycc.gov.uk.

High Lane, Haslemere, Notice of Road Resurfacing

Please read here the resident letter for the resurfacing work on High Lane, Haslemere. The letters are due to be delivered over the next couple of days.

NB High Lane Plan NB High Lane Mar
The works are scheduled to start on 23/0/3/17. Sometimes the council’s plans have to change, often due to bad weather or problems on other works in the same programme which can have a knock on effect. If anything changes with the details of these works, we will let you know.

You can also find up to date details of the works on www.surreycc.gov.uk/roadworks

If you have any questions please do not hesitate to contact the council on 0300 200 1003 or email works.communication@surreycc.gov.uk.

Forthcoming Street Works – A286 – Haslemere Road, Brook – from 17th February

Thames Water, following recent problems, are to improve their water supply network. In addition to replacing existing pipe work with new polyethylene pipes to improve water pressures and reduce leakage risk, there is a necessity to increase the existing pipe size significantly because of supply / demand problems in the local area especially during the hotter months which if not addressed may leave residents with reduced water pressure supply.

Work will start on 17th February 2017 and is anticipated to last around 5 weeks. Where possible extended working hours including weekends will be used to expedite the completion of the project.

NB A286

More information here in this resident leaflet.

Some Haslemere Highways updates

Here are some Highways/Parking updates for Haslemere –

Lower Street: The current proposed start date for road repairs in Lower Street is 20th January 2017 and the work will be completed at night for 1 day.  However, with the current weather, the repair date could change.

NB Lower Street

Kings Road:  Resurfacing is scheduled for 25th January 2017.  Sometimes plans have to change, often due to bad weather or problems on other works in the same programme which can have a knock on effect. If anything changes with the details of these works, we will let you know. This leaflet has been distributed to residents and local businesses and contains more information.

NB Kings Road

Sturt Road: Works are scheduled to complete by the end of January. I will have an exact date by Monday afternoon when I meet with the Surrey County Council highways team.

Residents can also find up to date details of the works on www.surreycc.gov.uk/roadworks

If you have any questions please do not hesitate to contact the council on 0300 200 1003.

Double yellow lines in the vicinity of St Bartholomew’s church: I have met the church and residents about this with Surrey County Council’s parking team. As a result of this, it has been agreed that a parking restriction scheme will be put in place here with yellow lining. It will be implemented this year. I have contacted the parking team to get an installation date.

Extended Double Yellows Hill Road/Midhurst Road: Extended double yellow have been agreed at the junction of Hill Road/Midhurst Road to improve sightlines. I await a date from the parking team.

Haslemere Independent County Councillor Update

Here is an update of my activities as Haslemere’s independent Surrey County Councillor over the past few weeks:

Meetings attended since my last update
Meetings attended at County Hall, Kingston

Mar 15, 2016 Full Council (Agenda, minutes and webcast here)

April 21, 2016 Economic Prosperity, Environment and Transport Board (Agenda and minutes here)

May 9, 2016 Haslemere Station Travel Plan finalising meeting with SCC Sustainable Transport team (link to final STP document)

May 10, 2016 Residents Association/Independents group meeting

May 17, 2016 Full Council (Agenda, minutes and webcast here)

June 9. 2016 Economic Prosperity, Transport and Environment Board (Agenda and draft minutes here)

July 5, 2016 Residents Association/Independent Group meeting

July 12, 2016 Full Council (Agenda here)

Waverley Local Area Committee meetings attended

Mar 16, 2016 SCC Highways Merrow, with Planning team to discuss PIC/SIO6 developer funding available for Haslemere highways schemes

Mar 18, Waverley LAC (Agenda and minutes here)

May 31, 2016 Waverley Youth Task Group, Godalming: presentations by Future Steps providing 1:1 Early Help, and Eikon outreach work as part of Waverley Local Prevention Framework.

Waverley youth task group - Eikon Bus

Waverley youth task group – Eikon Bus

June 17, 2016 Waverley Local Area Committee, Haslemere Hall (Agenda and draft here) See 2 paragraphs below:

Highways Budget 2016/17: Revenue Maintenance £237,173, Capital Maintenance £457, 242
Haslemere and Western Villages Task Group will receive approximately £120,000- to be divided equally. Of these funds 70% has to be spent on highway maintenance. I have been working with the Highways team on the list of priorities- to be finalised mid-July.  To include – drainage and highway surface improvement Sturt Railway Bridge and section of Sturt Road; sections of Kings Road, High Lane and Lower Street (at junction with Sandrock) resurfacing,
Project Horizon resurfacing: Blackdown Lane completed spring 2016, however Liphook Road-Sturt Road has been placed on a reserve list.  I am challenging this decision.

There is wide spread concern among councillors about the lack of information for members about Project Horizon, roads dropped from the list, little if any information about future plans.
Project Horizon 5 year Pavement Maintenance Programme – a new £21m scheme, an attempt to address an unacceptable level of deterioration of pavements.  Waverley LAC members raised their concerns that only one pavement scheme is planned in Waverley 2016/17 (a long stretch in Cranleigh) and that decisions over priorities were not based on local member knowledge.
I was re-nominated as the Waverley LAC committee representative on the SCC Friends and Family Committee

June 21, 2016 Waverley Local Area Committee private informal meeting, Farnham Town Hall

Haslemere Town Council meetings

Mar 17, May 12, June 30 2016 Haslemere Town Council – SCC Highways update and
Haslemere Railway station major works. Minutes/agenda here:

Meeting with HTC and SCC 17Mar16 – Minutes

Meeting with HTC and SCC 12May16 – Minutes

Meeting with HTC and SCC 10JUN15 – Agenda

South West trains are carrying out major improvements, a new cycle hub for 190 spaces is being built, works to improve the forecourt have just started and an additional deck on the station car park will commence in late August 2016.

Agreeing a forecourt design has involved many meetings, and numerous partners – including SWT, Network Rail, SCC Highways and Passenger Transport with input from Station Travel Plan survey findings.

The challenge is how to meet the needs of all station users, when there is such limited physical space – the station built in the 1850s was never intended to cope with 1.7 million passenger journeys/year.  Forecasts indicate passenger numbers will continue to increase, the large housing developments planned for Dunsfold, Bordon, Fernhurst and Midhurst will add further pressure on Haslemere station and the surrounding roads.  Building an additional deck on the carpark will provide an additional approx. 110 spaces, a temporary solution to the need for further parking capacity. I believe we need innovative, creative planning to cope with future demand, while maintaining the character of Haslemere as a small market town.
Disruption during the car park works, while challenging offers potential opportunities for travellers to find new ways of getting to the station- an on-line survey to www.surveymonkey.co.uk/r/haslemerestationaccess to see if there is demand for a Hoppa trial for commuters to the surrounding villages.  Passengers can also check out SCC Travel Smart website www.travelsmartsurrey.info for travel information to the station. For more information, read an earlier blog post here.

On June 14, 2016 a SCC/SWT communications event was held at the railway station: SCC Sustainable Travel Team ran Personalised Travel Planning training to passengers, SWT displayed forecourt and car park plans followed by an open community evening event at Georgian House Hotel.  (Link to recent plans).

SCC Sustainable Travel Team ran Personalised Travel Planning training to passengers

SCC Sustainable Travel Team ran Personalised Travel Planning training to passengers

SWT Travel event at the station

SWT Travel event at the station

Station Information Event

Station Information Event

Haslemere Station Community Rail Partnership

Mar 15, 2016 South West Trains stakeholder conference, SWT Basingstoke campus – SWT franchise ends June 2017, they plan to work with community on their franchise bid notably via the Community Rail Partnerships.

Mar 22, April 27, May 25, 2016 Haslemere Community Rail Partnership- established to promote Haslemere railway station as a “gateway” for visitors both to the town and the surrounding countryside, for the benefit of the businesses and town community. Improving the aesthetics and signage at the station forecourt and approaches is also a key goal.  The partnership has now been formally registered with ACorP- the national Association of Community Rail Partnerships.  Benefits include match funding for station forecourt improvements from SWT, with statutory agreement for future franchise holders to continue this funding support.  The previously vacant station shop has now been refurbished as a community information hub.
Haslemere Highways site visits and key issues.

Local Highways Issues

I have organised regular site meetings with residents, and SCC Highways and parking teams. Issues addressed include Critchmere – property flooding issues, Hindhead – pedestrian crossing, St Bartholomew’s Church and Tanners Lane – parking and concerns over pedestrian safety, Woolmer Hill – parking/bus blocking,

Three Gates Lane, traffic speed reduction ITS scheme is still incomplete: SCC Road Safety Working Group has explained that this is due to a back log of VAS (Vehicle Activated Signs) installations and the need for traffic management during the works, the 2 funded new VAS on the approaches to Three Gates Lane have unfortunately been delayed for over a year.  Currently planned for July/August, 2016.

Shepherds Hill/Lower Street highways works to improve pedestrian safety, completed May 2016.

Weyhill zebra crossing, works started late June, 2016 – currently the footway has been left purposely unfinished to allow the electricity board and Skanska to go in and supply the columns. Snagging to the unfinished section has been carried out, Keir have been asked to make some changes to improve it. It is hoped the electricity board will be going in very soon to carry out the works.

Bunch Lane, additional wooden posts to prevent verge parking to be installed.

Lower Street/Shepherds Hill pocket park – Town Council have asked to take ownership from SCC, still awaiting confirmation of the legal costs involved.

Some of the local events attended:

Mar 17, 2016 Woolmer Hill School music concert – contributed £680 funding from my members allocation

Left to Right for photograph Susan Stathers (Chair of Governors), Toby U (Yr7), Clare Talbot (Headteacher), Matthew Nash (Head of Music), Mille B (Yr 9), Nikki Barton, County Councillor, Eloise H (Yr 7)

Left to Right for photograph
Susan Stathers (Chair of Governors), Toby U (Yr7), Clare Talbot (Headteacher), Matthew Nash (Head of Music), Mille B (Yr 9), Nikki Barton, County Councillor, Eloise H (Yr 7)

April 19, 2016 Haslemere churches meeting to support local councillors, Camelsdale Vicarage

April 23, 2016 HM Queen Elizabeth II 90th birthday parade, Haslemere (more here)

April 24, 2016 St Georges Parade, Beacon Hill – all local scouting groups

May 2, 2016- Haslemere Charter Fair, judged the Town Crier competition (more here)

May 17, 2016 Brexit Debate – Haslemere Hall, Paddy Ashdown and Lord Forsyth lively debate in a very packed Hall

Paddy Ashdown (Remain) and Lord Forsyth (Leave) with compere in middle of picture

Paddy Ashdown (Remain) and Lord Forsyth (Leave) with compere in middle of picture

May 19, 2016 Mayor making, Sahran Abeysundara confirmed as new Mayor for Haslemere, Town Hall and July 10, Mayors Civic Ceremony, Haslemere Hall

June 16, 2016 Eagle Radio interview on station works and Station Travel Plan

June 29, 2016 Haslemere Vision Community Land Trust meeting, Haslemere Museum

Surrey County Council Members Allocation 2016/17

Haslemere Waverley Skatepark Open Day, August 11, 2016: Provided £500 grant towards the £2,000 costs of the event. The all-day event of workshops and competitions will be open to all skateboarders and bmx riders ages 7-16 years.

Any Haslemere community group is invited to contact me to apply for a grant, please see previous update (here and here) for a list of grants awarded previously.

Surrey CC Post Brexit

Rising demand for essential services while government funding is falling, SCC is being squeezed from both ends and this is set to continue.   Despite plans to save more than £80 million from the SCC budget this year, the increasing demand and cost pressures on SCC services will wipe these savings out.
The increase in demand for social care services account for the vast majority of this, with pressure set to continue.  By 2020 there will be an additional 6,500 Surrey residents over the age of 80 – many of them needing our support.  As the population of the county grows, SCC is also expected to provide thousands of additional school places, as well as improve the road network and dispose of Surrey’s waste.
Surrey is a significant net contributor to the national exchequer, yet receives one of the lowest financial settlements from the government in return.

Update: Haslemere railway station forecourt improvements

Work to improve the railway station forecourt in Haslemere by South West Trains (SWT) commences on Monday 4 July. The phasing and delivery has been planned to have minimal impact on how you currently use the forecourt and SWT have included night work to aid in this.

South West Trains' notice at Haslemere station

SWT notice at Haslemere station

South West Trains’ forecourt poster (thumbnail above)

Architectural drawing of forecourt improvements

Existing Haslemere forecourt drawing

Temporary Prohibition Traffic Notice – Wey Hill/Farnham Lane/St Christopher’s Road, Haslemere

NOTICE
THE SURREY COUNTY COUNCIL
WEY HILL (B2131), HASLEMERE
TEMPORARY PROHIBITION TRAFFIC NOTICE 2016

SURREY COUNTY COUNCIL IN EXERCISE OF ITS POWERS UNDER SECTION 14 (2) OF The Road Traffic Regulation Act 1984 and of all other enabling powers hereby gives notice that no person shall cause or permit any vehicle to enter or proceed in that length of Wey Hill (B2131), Haslemere that extends from its junction with Farnham Lane (D134) and its western junction with St Christopher’s Road (D5521) and/or any part and/or parts therein.

This Notice is required to enable highway maintenance, improvement and/or resurfacing works to be carried out on behalf of Surrey County Council. The Notice will come into effect on 11th July 2016 for a period of 5 days however these works are anticipated to be carried out between the hours of 22:00 and 06:00 within 2 nights of this period. The prohibition will only operate when the relevant traffic signs are displayed and to the extent indicated by those traffic signs.

The prohibition referred to above will not apply in respect of anything done:
a) with the permission or at the direction of a police constable in uniform;
b) in accordance with any restriction or requirement indicated by traffic signs placed on the highway by or on behalf of the Police.
Access for emergency vehicles, residences and businesses will be maintained at all times.

All eastbound vehicular traffic except buses and HGVs over 12’ height will be diverted via Wey Hill, Lion Green, Junction Place, Liphook Road, Sturt Road, Bell Road, Midhurst Road, Shepherd’s Hill, Lower Street and Wey Hill.

All westbound vehicular traffic except buses and HGVs over 12’ height will be diverted via Wey Hill, Lower Street (eastbound), Lower Street (westbound), (to follow gyratory due to the prohibited right turn at Shepherd’s Hill) Shepherd’s Hill, Midhurst Road, Bell Road, Sturt Road, Liphook Road, Junction Place, Lion Green and Wey Hill.

Buses and HGVs over 12’ height will be escorted through works by banksmen.